Route
18 project in New Brunswick begins
$200
million project will fully reconstruct Route 18 and provide congestion
relief; largest project in DOT's budget
(New
Brunswick) Today, New Jersey Department of Transportation
(NJDOT) Commissioner Jack Lettiere was joined by U.S. Rep. Frank
Pallone (NJ-6 th), New Brunswick Mayor James Cahill and a variety
of officials to break ground on the Route 18 reconstruction project
in New Brunswick. The project will fully reconstruct a
dilapidated stretch of Route 18 from Route
1 to the NJ TRANSIT/Amtrak Northeast Corridor rail bridge and
add auxiliary lanes in both directions to reduce the extreme congestion
caused by vehicles coming in and out of downtown New Brunswick.
"Route
18 is an outstanding example of the tremendous transportation needs
we have in New Jersey merely 1.8 mile long stretch of road that
will require $200 million in federal funds. It certainly
highlights the importance of the work Senators Corzine and Lautenberg,
Congressman Pallone and the rest the New Jersey Congressional
Delegation did in passing a new federal transportation bill that
will bring home more federal dollars to New Jersey and will allow
us to fund more desperately needed projects like Route 18," noted
NJDOT Commissioner Jack Lettiere.
"This
long-awaited Route 18 reconstruction project is crucial to support
on-going economic development projects in New Brunswick and the
growth of Rutgers University in New Brunswick and Piscataway," U.S. Senator Jon S. Corzine
said. "It is a project worthy of the federal support it has received,
including the $10 million in funding which was included in the
transportation bill which just passed the Congress last week."
"Today's
groundbreaking marks the beginning of improvements that will reduce
traffic congestion and increase mobility throughout New Brunswick
and Rutgers University," said U.S. Senator Lautenberg. "As one
of the key negotiators who hammered out the final Highway bill,
I understood the importance of this project for the region. Transportation infrastructure is essential for New Jersey so we
must do all we can so every commuter has the smoothest, safest
ride possible."
"New
Jersey DOT has developed an innovative plan for Route 18 that
will correct serious traffic and safety problems that have plagued
the highway in recent years," Congressman Pallone said. "Congress showed its commitment to this project by including it
in the transportation bill passed last week. I'm looking forward
to a quieter, safer and less congested Route 18 when DOT completes
its work in four years."
The
reconstruction of Route 18 will take over 4 years to complete
with the expected project completion in Summer of 2009. It is one of the most complex construction projects in state history
and is the largest project in NJDOT's FY 2006 Capital Construction
Program. Route 18 in New Brunswick is one of the most heavily
congested corridors in the state with over 80,000 cars per day
and services vehicles heading into downtown New Brunswick and
major entities such as Rutgers University, Johnson & Johnson's
Corporate Headquarters, Saint Peter's University Hospital and
Robert Wood Johnson University Hospital.
Due
to the potential serious traffic impacts to users of Route 18
during construction, NJDOT has embarked on its largest ever community
partnering effort to work with the entire New Brunswick and surrounding
community on traffic mitigation efforts. The partnering
effort has helped mold the project's construction schedule to
have the least possible impact on Route 18 motorists, taking into
account factors such as city residents' concerns, Rutgers University
scheduling, and the health care and corporate community's needs. Each piece of the traffic mitigation effort has been written
into the construction contract and will be strictly adhered to
by the construction contractor, Conti Enterprises.
Additionally,
NJDOT has hired a full-time on-site communications professional
to address day to day community concerns about the project and
has created a comprehensive Route 18 reconstruction web site that will be updated
as the project moves forward. The web site will also provide
access to on-road cameras that will let motorists know what the
traffic conditions are on Route 18 before they begin their commute.
"Anyone
who has driven Route 18 knows this project was desperately needed both
from a safety standpoint and from congestion relief standpoint. While we are making every effort to make the construction
process as painless as possible for motorists, we are still asking
for drivers' patience as this project moves forward," noted Lettiere. "While the construction may try your patience, please remember
that the end product will produce a vastly better Route 18. I can point to the Route 18 extension just down the road in Piscataway
as an outstanding example of how we can drastically improve your
ride with major improvements."
Listed
below are some of the extensive steps NJDOT is taking to ensure
the project causes as little disruption as possible and the project
schedule:
Traffic
Mitigation
Lane
Closures
As
a part of NJDOT's comprehensive traffic mitigation plan, the contractor
will have to adhere to the lane closure schedule listed below.
NJDOT will strictly enforce the set lane closure parameters
with fines ranging from $10 to $20 for every minute the contractor
has closed a lane improperly.
Route
18, Northbound and Southbound
All
lanes must remain open:
Monday thru Friday 6:00 AM to
9:00 PM
Saturday 8:00 AM to 8:00 PM
Sunday 9:00 AM to 8:00 PM
Minimum
of two lanes must remain open (in the three lane section)
Monday thru Thursday 9:00 PM to
6:00 AM
Friday 9:00 PM to 8:00 AM
Saturday 8:00 PM to 9:00 AM
Sunday 9:00 PM to 6:00 AM
Minimum
of one lane must remain open (in three or two lane section)
Monday thru Thursday 11:00 PM
to 5:00 AM
Friday 11:00 PM to 6:00 AM
Saturday 11:00 PM to 6:00 AM
Sunday 11:00 PM to 5:00 AM
No
work that will interfere with the flow of traffic will be permitted
on the day Rutgers graduation, home football games or major sporting
events.
No
lane closures will be permitted during holidays.
There
is a similar lane closure schedule for Route 1, Route 27, and
Route 172, but closures on those roads will not be as often or
have the impact of Closures on Route 18.
**Emergency
work that is necessary to ensure safety is a permissible reason
to violate the lane closure plan.**
Incentives
and Disincentives
For
each stage of the construction, NJDOT will monitor the progress
and impose incentives or disincentives to the contractor, i.e.
monetary rewards for work completed early and fines for work completed
late. Each stage of the construction is required to be
completed within a certain time frame. A detailed incentives/disincentive
plan written into the construction is another step NJDOT is taking
to ensure the most expeditious possible completion of the project.
Some
of the highlights of the incentive/disincentive plan are:
Disincentives/fines
-
For the completion of the Route
27 Underpass, which requires a one-time closure of Route 27, the
contractor can be fined $2,000 for every hour the work is late. Only 77 hours are permitted for this stage
-
For the completion of the New
Street Bridge, the contractor can be fined $5,000 for every day
the work is late. Only 338 days are permitted for this
stage.
-
For the completion of the Route
1 Southbound to Route 18 ramps, the contractor can be fined $10,000
for everyday the work is late. Only 31 days are permitted for
this stage.
Incentives/rewards
-
For the completion of the Route
27 Underpass, which requires a one-time closure of Route 27, the
contractor can receive additional payment of $2,000 for every
hour the work is completed ahead of schedule. Payments
are not to exceed $46,000.
-
For the completion of the New
Street Bridge, the contractor can receive additional payment of
$5,000 for every day the work is completed ahead of schedule.
Payments are not to exceed $400,000.
-
For the completion of the Route
1 Southbound to Route 18 ramps, the contractor can receive additional
payment of $10,000 for every day the work is completed ahead of
schedule. Payments are not to exceed $100,000.
Project
Schedule
Web site construction schedules
Below
is the immediate and long-term construction schedule for the project.
The long term schedule is a broad outline as conditions
in the field can quickly alter the schedule. Each month
NJDOT's Route 18 Reconstruction web site will list the specific
work ongoing during that particular month.
Schedule
for August
The contractor
will re-stripe lanes to shift traffic so that barrier curbs can
be installed.
-
Barrier curbs
will be placed from just south of New Street to just south of
George Street. All of the work will take place in the median where
crews will be removing the grass.
-
This will
be followed by paving within the median and along portions of
shoulders. Some lanes closures will begin in mid-August
-
Tree clearing
will continue.
-
Rough grading
for utilities will take place from Paulus Boulevard to Newell
Avenue on southbound side.
-
Safety drums
will be put in place on the northbound roadway.
Long
Term Schedule
-
Stage 1- Summer 2005-Fall 2005
Traffic Pattern Changes:
Close Crest Road access
Construction:
Temporary paving to allow traffic shifts, Albany Street between Neilson and Burnett Streets, and Route 18
resurfacing between Route U.S. 1 and Paulus Boulevard
-
Stage 2 Winter 2005-Fall 2006
Traffic Pattern Changes:
Close New Street Interchange and Commercial Avenue jug handle. Activate double left turns from Route 18
northbound to Commercial Avenue. Close southern Carpender Road and Dewey Drive access. The Route 27 Underpass
construction will require a weekend closure of Route 27 between River Road and Burnett Street.
Construction:
New Street bridge and roadway reconstruction, Route 18 southbound between Richmond Street and George Street,
Carpender Road pedestrian bridge, Paulus Boulevard, and Route 27 Underpass
-
Stage 3 Fall 2006-Fall 2007
Traffic Pattern Changes:
Open New Street Interchange. Close Commercial Avenue, Burnett Street, and the Route 27 to Route 18
southbound Ramp. Johnson Drive to be maintained during staged construction.
Construction:
Commercial Avenue reconstruction, Route 18 southbound between the Northeast Corridor bridge and
Richmond Street including the western 1/3 of the bridge over Route 27 and Johnson Drive, and Paulus
Boulevard jug handle
-
Stage 4
Traffic Pattern Changes: Open Route 18 southbound ramps at
Commercial Avenue and close Route 18 northbound ramps to Route 27.
Construction:
Commercial Avenue bridge and Route 18 northbound (local) between Boathouse Drive and Northeast Corridor
bridge including the eastern 1/3 of the bridge over Route 27 and ramps to Route 27
-
Stage 5
Traffic Pattern Changes:
Open Commercial Avenue intersection and bridge. Open Route 18 northbound ramps to Route 27. Close George
Street bridge and ramp.
Construction:
George Street Bridge, Route 18 freeway between Commercial Avenue and the Northeast Corridor bridge, and
Route 18 southbound between George Street and Paulus Boulevard.
-
Stage 6
Traffic Pattern Changes:
Open George Street ramp to Route 18 southbound, and Route 18 freeway from Route U.S. 1 to Northeast
Corridor bridge.
Construction:
George Street Bridge, Route 18 northbound (local) between Paulus Boulevard and Boathouse Drive, and Route 27
between Burnett Street and the Raritan River.
-
Stage 7
Traffic Pattern Changes:
Open George Street bridge and intersection. All traffic movements are open.
Construction: Route 18 northbound freeway shoulder between Paulus
Boulevard and Boathouse Drive
-
Stage 8
Traffic Pattern Changes:
All traffic movements are open.
Construction:
Route 18 median between Route U.S. 1 and Boathouse Drive.
Estimated project construction duration is 50 months, with substantial completion
by Summer 2009.