Christie Administration
highlights progress
in reconstruction
of Sandy-damaged Route 35
on
Barnegat Peninsula
Complete Streets proposals for
bicyclists and pedestrians detailed
(Seaside Heights) New
Jersey Department of Transportation
(NJDOT) officials today visited
with Seaside Heights Mayor William
Akers and other local officials
to assess progress in the $265
million project to rebuild a
12.5-mile segment of Route 35
on the Barnegat Peninsula that
was severely damaged by Superstorm
Sandy.
Officials also detailed Complete
Street components of the project
for pedestrian and bicycle accommodations
and previously announced plans to
suspend construction activities
along most of Route 35 during the
summer.
The Administration understands
that residents and business owners
have endured great hardships
as a result of Sandy and that they
want nothing more than for life
to return to normal, Commissioner
James Simpson said. I am
pleased to report that we have
made a great deal of progress
in seven months, but much work remains.
While work has progressed on schedule
in some areas, such as the Route
35/Route 37 interchange in Seaside
Heights, unforeseen underground
conditions and harsh winter weather
challenged contractors' efforts
to keep pace with a very aggressive
schedule. NJDOT expects most
of the work to be completed by the
summer of 2015.
The project has been divided into
three sections covering mileposts
0-4, 4-9 and 9-12.5, with one construction
contract awarded for each section.
Major construction activities began
this past September and significant
progress has been made in all three
sections.
Complete Streets
Bicycle Accommodations
The Department also announced
that it has made great strides
incorporating Complete Streets bicycle
accommodations (pdf
36k) into
the project design. NJDOT plans to
create bike lanes on Route 35 for
nearly ten miles of the 12.5-mile
length of the project. In some areas
where space is tight, bicyclists
will share the road or be diverted
to parallel roads.
The Department has met with officials
from all eight municipalities to
gain support for the plan that accommodates
bicycles and balances the need for
parking in some areas.
Pedestrian Accommodations
The Complete
Streets plan for this project includes:
- 63,000 linear feet of new
or rebuilt sidewalk, including
a continuous sidewalk along
the entire 12.5 miles of the
northbound lanes
- 1,200 ADA ramps
- 200 pedestrian countdown
heads to promote safe use of
crosswalks
- The addition of a Pedestrian
Hybrid Signal just north of
the Route 37 interchange to
promote safe pedestrian access
to the bay in Seaside Heights
Construction Progress
Last summer, Governor
Chris Christie announced the
start of
the $265 million construction
project to rebuild Route 35,
a state highway along the New
Jersey coastline that sustained
heavy damage during Superstorm
Sandy. The
federal government will be
providing 80 percent of the
total project costs with Sandy emergency
relief funds, with the balance
paid by the state.
In each section, the highway will
be completely rebuilt. The
new stone-and-asphalt roadway
will be two-feet thick, providing
a more stable road and smoother
driving surface. A new storm-water
drainage system has been designed
to handle 25-year storms and
will feature nine pump stations
and treatment facilities to filter
and purify the storm water prior
to discharge into Barnegat Bay.
Contract 1,
covering the portion of the
project from milepost 9 to
milepost 12.5 in Mantoloking
and Bay Head, was awarded to
Agate Construction Co., for
$36 million. In this section,
Route 35 consists of a single
roadway offering just one travel
lane in each direction with
shoulders.
By Memorial Day, when Agate will
suspend all work for the summer,
2.5 lanes-miles of Route 35 are
expected to be completed, including:
- both the northbound and southbound
lanes from Osborne Avenue to
Lyman Street
- the southbound lane from
Downer Avenue to Curtis Point
Drive in Mantoloking
Agate also has made significant
progress constructing pump stations
on Downer and Goetze Street, two
of the four pumps stations being
built in this section. To date,
Agate has installed more than 25,000
linear feet of water, sewer, and
drainage pipes.
The Department established a very
aggressive construction schedule
for the contractors, with the hope
that work in this section could
have reached substantial completion
by this summer. However, work
in this section will need to continue
in early September.
Contract 2 covers
the section of the highway from
milepost 4 to milepost 9, in
Brick, Toms River, and Lavallette.
This contract was awarded to George
Harms Construction Co. for $101
million.
Route 35 southbound between Strickland
Boulevard in Toms River and 6th
Avenue in Brick is expected to
be complete by summer 2014. To date,
the contractor has installed
more than 61,000 linear feet of
water, sewer, and drainage pipe
in this section.
Contract 3 encompasses
the southernmost section of the
highway between milepost 0 (at
the entrance of Island Beach
State Park) to milepost 4. The highway
extends through Berkeley, Seaside
Park, Seaside Heights, and Toms
River in this section. The
contract was awarded to Union
Paving & Construction
Co., at $80.7 million. In this
section, Route 35 is generally
a divided highway, providing two
travel lanes in each direction.
By the time work on Route 35 is
suspended for the summer on June
13, 2014, completed work is expected
to include:
- the Route 37 eastbound ramp
connection to Route 35 northbound
(for Seaside Heights)
- a stretch of the Route 35
southbound expressway (running
along the Barnegat Bay) between
6th Avenue in Ortley Beach
(Toms River) and the Route
37 interchange in Seaside Heights
- the installation of drainage
pipes and the rebuilding three
lane-miles of Route 35 northbound
from Central Avenue/Dewey Drive
in Seaside Heights to 6 th
Avenue in Seaside Park.
To date, Union Paving has installed
more than 20,000 linear feet
of water, sewer, and drainage pipe.
Public Outreach
NJDOT
has a robust community outreach
effort to help residents and
business owners communicate their
concerns to NJDOT and stay informed
of construction activity. That
effort includes a hotline telephone
number, 732-230-7356, and an
email address, restorenj35@mbi-gs.com.
Since July, the public outreach
team has handled more than 3,000
emails and hundreds of phone
calls, in addition to face-to-face
conversations with residents
on a daily basis. In addition, the
Department created
a project-specific website that
provides information on construction
activity. The site will be
updated as work advances.
Summer Work Suspension
On March 20, NJDOT announced the
suspension of construction activities along
most of Route 35 during the summer
to ease congestion during the
busy vacation season. Ten miles
of the 12.5-mile construction
zone will have the full complement
of travel lanes on Route 35 available.
This also ensures mobility for
emergency responders during the
busy summer season and maintains
public safety because Route 35
serves as a primary evacuation
route for the peninsula.
|