|
Route 15 Study
Executive Summary
Discussion |
Objectives |
Concepts |
Conclusion
This
web site has been
archived and is
no longer being
updated. |
Background
The Route 15 Corridor Study was initiated in 1998 from
the North Jersey Transportation Planning Authority (NJTPA)
Study and Development Work Program. The first phase
of the study consisted of determining what the needs
or the problems were within the corridor. One of the
immediate issues was that Route 15 did not fit within
the existing NJTPA's
defined corridors. The New Jersey Department of Transportation (NJDOT) proposed creating a new corridor
of study for Route 15 and Route 206. This request was
submitted to NJTPA for approval before the Multimodal
Alternative Analysis and Concept Development studies
commenced. NJTPA agreed that the study proposal was
reasonable; however, they declined to add the proposed
new corridor to their present Regional Transportation
Plan update. Based on the results of the Route 15 Corridor
Study, NJTPA may consider adding this proposed corridor
in the future.
Another
issue related specifically to the transportation problems
within the corridor. Deficiencies related to safety,
pavement, bridges, drainage, geometrics, and mobility
were collected. When the needs were identified, NJDOT
held outreach meetings with local officials, business
owners, and elected officials. NJDOT received comments
on the identified needs that were incorporated into
the Needs Assessment phase of the study and subsequent
report. With a consensus regarding the needs, it became
clear that roadway capacity increases would need to
be considered in the next phase and that a Mulitmodal
Alternative Analysis would be required. The concepts
presented here were derived in conjunction with this
analysis. The need for the capacity improvements recommended
could not be eliminated by the alternatives. However,
several complimentary strategies were identified. It
is important to the future viability of the corridor
to implement these complimentary strategies.
Discussion
Route 15 is a diverse corridor that presents a myriad
of issues pertaining to the development of possible
transportation improvement concepts. These issues must
be analyzed and taken into consideration when concepts
are proposed. In determining possible concepts for the
identified needs within the corridor, system level transportation
constraints are critical. The solution for one roadway
cannot create or worsen the situation on another roadway.
The problem cannot just be moved to another location.
From a roadway perspective, we cannot continue to build
our way out of congestion. In all studies that show
a need to add capacity, a detailed analysis is conducted
to determine what other possible strategies can be used
in lieu of or in addition to a widening or bypass. As
demand increases, the number of lanes necessary to permit
an equivalent amount of travel by vehicles goes beyond
the realm of what can or should realistically be built.
In
determining the final concepts, NJDOT had several meetings
for both the local and elected officials as well as
the general public. A web site focusing on Route 15
was established for the public to both learn about the
study and to provide input. A Community Assessment was
conducted that tried to determine the community vision
for each municipality within the corridor so that the
concepts developed would be within the context of the
surrounding communities and not just for the road user.
As a final check for the concepts, The New Jersey State
Development and Redevelopment Plan, (SDRP), was reviewed.
The concepts presented in this summary are meant to
pose possible engineering solutions to identified problems
tailored around community-recognized issues, constraints,
and opportunities.
The
corridor is divided into five different sections for
discussion: Dover/Wharton; Rockaway/I-80; Jefferson;
Freeway Section; Sparta/Lafayette. Each section has
its own unique characteristics and issues that have
to be addressed. The study does not recommend adding
lanes to Route 15 through the entire corridor, but there
are concepts to widen segments of the roadway and/or
to bypass the existing alignment. The corridor has been
studied as a whole to determine what makes sense not
only for the individual municipalities, but also for
the region. The overall study strives to maintain a
road system of continuity.
Objectives
As a result of the considerations listed in the above
discussion, the objectives for the concepts are to address
the identified need while: maintaining a transportation
system level balance; incorporating multimodal transportation
uses; meshing with the locally identified context of
the surrounding community; conforming to the strategies
of SDRP; and striving for a continuity of level of service.
Concepts:
See
Figure
1 - Near Term Potential Concepts Map (pdf 73kb)
See Figure
2 - Long Term Potential Concepts Map
(pdf 71kb)
You will need Adobe Acrobat Reader to view these
maps. You can download Adobe Reader for free
at our State
Adobe Access page.
Dover/Wharton
Three primary concepts were developed for Route 15 from
its southern terminus in Dover at the intersection of
Route 46, north through the retail area of Wharton.
These are identified on Figure
1, south of I-80. A complimentary strategy
for this section is to provide local access and pedestrian
accommodations in proposed improvements between Essex
Street and Mount Pleasant Avenue.
Bridge Replacements (CPM):
The first concept supports
an active NJDOT project presently in the Feasibility
Assessment phase. Two bridges are slated for replacement.
Currently, the bridge replacement projects may involve
replacing one bridge while eliminating the other bridge
and putting a T-intersection at Rt. 15 and Rt. 46.
Alternatives are being studied. If Rt. 15 and Rt.
46 are changed to a T, then an opportunity exists
for the Department to return what are essentially
local streets back to the municipality. From a context
sensitive design perspective, this would be ideal
as the existing problems include access and geometric
deficiencies as well as safety concerns related to
over-represented accidents at Dover's local intersections.
Removing this traffic from the local roads would be
ideal, but the ramifications to the intersections
are still under review.
Bicycle/Pedestrian:
The second concept involves the need to correct deficiencies
between Route 46 and Mount Pleasant Avenue. The segment
needs mobility improvements for pedestrians and bicyclists
such as sidewalks, crosswalks, handicap ramps, and
bicycle-safe inlet grates. Access deficiencies should
also be evaluated within this concept.
Developer
Improvements with Enhancements: Rockaway 80, a
developer, is to make improvements to the intersection
of Route 15 and Mount Pleasant Avenue which will include
widening north of the intersection. A second developer
(Costco/Shop Rite) is to meet the Mt. Pleasant improvement
and widen northbound to the Dewey Avenue intersection
with the Costco driveway. This study concurs with
the need to make both developer improvements as identified
by the NJDOT Bureau of Major Access Permits and further
suggests some restriping of the turning lanes and
a southbound widening to carry two lanes southbound
until after the Mt. Pleasant Avenue intersection.
The environmental screening identifies a stream crossing
and wetlands adjacent to Mt. Pleasant Avenue where
the southbound widening may require widening the bridge
over Green Pond Brook.
Rockaway/I-80
This section of the Route 15 corridor has two concepts
with important regional implications. These concepts
are identified on Figure
1 and Figure
2.
Complete
the Missing Moves at the I-80/Rt. 15 Interchange:
The I-80/Rt. 15 interchange is missing the following
moves: I-80 eastbound to Route 15 southbound; I-80
eastbound to Route 15 northbound; Route 15 northbound
to I-80 westbound. Many geometric, structural, and
pavement deficiencies can be addressed together by
providing the missing ramps. Safety concerns will
also be addressed by removing the "missing movement"
traffic from the local streets.
Developer
Improvements with Enhancements: The developer
(Highlands at Morris) will widen northbound Route
15 to provide three lanes consistently from I-80 to
Phipps Road. Southbound Route 15 will be widened to
Main Street again providing a consistent three-lane
section. The developer will also put in a traffic
signal southbound and new access for the development.
This study supports the developer improvements as
a minimum.
Several
alternative concepts were evaluated for this area
with suggested widenings to four and five lanes in
each direction and widenings of approaches for the
cross streets. To recommend these concepts would be
inappropriate. The existing system cannot handle the
traffic that exists today. Route 15 traffic feeds
onto I-80 with such force that mainline I-80 cannot
absorb the traffic. A backup onto both I-80 and Rt.
15 is the result. The developer improvements proposed,
while adding more capacity to handle the additional
development, also meters the southbound flow by adding
a traffic signal. The net result should be a continuation
of the traffic flow that exists today. If Route 15
were widened beyond the recommended three lanes, I-80
could not handle the traffic. I-80 would experience
a system level failure and an environmental, societal,
and financial detriment for both commuters and residents.
On
the other hand, the developer's widening to three
lanes will not provide desirable operations for the
next twenty years. However, given that, north of this
section, Route 15 runs through both Rural and Environmentally
Sensitive Planning Areas according to The New Jersey
State Development and Redevelopment Plan, (SDRP),
future traffic demand should be tempered by the type
of development and patterns of growth in the years
to come. Extensive, low density and dispersed growth
to the north will result in a need for five lanes
in each direction in this section, which is undesirable
and cannot be supported within the existing transportation
system.
As
a result, the best concept seems to be the one that
maintains a balance between I-80 and Route 15 as it
currently exists, giving a slight advantage to the
Route 15 commuters. Therefore, the developer's improvements
are consistent with the concept that provides the
best working solution for this section of the roadway
and was the concept presented to the public. A widening
to four or five lanes is a concept that cannot, and
should not, be pursued at this time. Any potential
travel demand beyond what is provided by this concept
should be addressed through growth management strategies
consistent with the SDRP and appropriate Travel Demand
Management strategies. Additionally, a proposal to
initiate passenger service on the New York Susquehanna
and Western freight line can also play a role in managing
the future growth by removing these road users from
the highway system.
Jefferson
Township Area
The Jefferson section of the corridor has two major
concepts as well. Complimentary strategies identified
within Jefferson Township include leasing existing parking
spaces for a park-and-ride lot and NJ TRANSIT's
studying the idea provision of bus transit service from
the Picatinny Arsenal to Dover. Additionally local access
and pedestrian accommodations need to be considered
in the proposed improvement plans for Route 15 southbound
between south of Lake Hopatcong and the U-turn ramp
to Route 15 northbound. The concepts are identified
on Figure1
and Figure
2.
Intersection
Redesign at Berkshire Valley Road: The Berkshire
Valley intersection has several issues that need to
be addressed by a redesign: congestion; safety; access;
mobility; and geometry. Several possible concepts
were identified for this location although none will
provide desirable levels of service more than twenty
years into the future. The over-represented left-turn
accidents point to a need to make improvements. Although
the concepts do not accommodate travel demand for
more than twenty years, again, there is a need to
consider the other system level issues. If this intersection
is improved to provide maximum flow, it will change
the character of this business section as well as
push more traffic down Route 15 to the I-80 interchange.
Any potential travel demand beyond what is provided
by this concept should be addressed through growth
management strategies consistent with the SDRP and
appropriate Travel Demand Management strategies.
Widening
through the commercial area: The area between
Edison Road and Bowling Green Parkway is Jefferson's
commercial district denoted by a high driveway density
and with a potential for pedestrian activity. Because
the state highway environment is a three or four lane
roadway carrying 4000-5000 vehicles per hour at 40-50
m.p.h., a concept of relocating Route 15 southbound
outside the commercial area was suggested. Such a
concept would have a significant environmental impact
and although it would provide a better local environment,
the trade off in this case does not seem to warrant
the investment to the detriment of the environment.
Through our public outreach, the municipality did
not clearly indicate any interest in pursuing a bypass
and, in respect of local preferences, this concept
will not be pursued.
Various
concepts were analyzed for this area including widenings
up to four lanes in each direction. Although such
widenings would provide acceptable operations through
2018 in this section, traffic congestion would only
be pushed further south. Currently, Route 15 northbound
is three lanes to Edison Road while southbound is
only two lanes. Intersection improvements are needed
at both Edison Road and Bowling Green Parkway for
northbound Route 15. One suggested concept is to put
a jughandle in at the existing signalized intersection
at Edison and "T" the Bowling Green Parkway
intersection by converting it into a cul-de-sac west
of the intersection. A collector road could be built
within the existing median between the northbound
and southbound alignments of Route 15 to provide adequate
mobility through this commercial area. Northbound
Route 15 would be widened north of Edison and southbound
Route 15 would be widened to provide a consistent
three-lane section through this area. An alternative
concept would include the specified widenings, but
would require a new traffic signal and an additional
turning lane for eastbound Bowling Green Parkway.
A collector road is still recommended, but a jughandle
at Edison Road is not. For both concepts, Route 15
southbound turning lanes should be considered with
acceleration/deceleration lanes.
Freeway
Section
The freeway section starts in northern Jefferson Township
and proceeds north through Sparta Township. Two concepts
are proposed within these limits are listed on Figure
1 and Figure
2.
Truck
climbing lane: One concept is to provide a southbound
truck-climbing lane south of County Route 517. This
improvement can be made in conjunction with the culvert
rehabilitation and will resolve the deficiency of
the short acceleration lane from 517.
Park-and-ride
expansion: The recommended expansion of the Blue
Heron Park-and-Ride involves relocating the existing
on-ramp for Route 15 northbound to north of Blue Heron
Road which would eliminate an existing weave between
the on- and off-ramps. Expanding the park-and-ride
is a complimentary strategy that was identified by
the multimodal alternative analysis that at the same
time will create a better exit from and entrance to
Route 15.
"End-of-freeway"
safety and congestion problems are to be resolved
by the widening concept proposed in the next section.
Sparta/Lafayette
Two capacity increases are proposed for the remaining
section of Route 15 and are noted on Figure
2. The section is divided into two different
types of increases due to the traffic flow and characteristics
of the areas. The first concept proposes a widening
from the end of the freeway section at Route 181 to
Route 94. The second concept is to bypass the village
of Lafayette from Route 94 to Route 206. The Multimodal
Alternative Analysis suggests that NJ TRANSIT
should study the possibility of bus transit routes from
Sparta to Morristown and Ross's Corner to Newark. Another
complimentary strategy is to lease park-and-ride spaces
in the vicinity of Route 15 and Route 94. These strategies
as well as local access and pedestrian accommodations
on Route 15 between Route 94 southbound/Limecrest Road
and Beaver Run Road, do not negate the need for capacity
increases, but are suggested to help maintain the available
roadway capacity in the corridor. In the long term,
the proposal to initiate passenger service on the New
York Susquehanna and Western freight line can also play
a role in managing the future growth. If service extends
from Sparta, motorists will have a new and convenient
alternative to driving. Various strategies will have
to be implemented to maintain a viable transportation
system.
Proposed
widening: The proposed widening from Route 181
to Route 94 will require an Environmental Impact Statement
(EIS) which will consider all possible alternatives
that meet the purpose and need of the potential project.
From a conceptual perspective, a widening along the
existing alignment seems to be the best way to minimize
any environmental impacts in this sensitive area.
Such a widening without the need for an off-alignment
freeway could accommodate the land use and traffic,
but any determination will be made through the course
of the EIS. Regardless of the final outcome, the intersections
of Wilson and White Lake Roads should be realigned
to provide one signalized intersection instead of
two separate intersections.
Proposed
Bypass: The second concept is a bypass or widening
of Route 15 through Lafayette. While the projected
traffic volumes could be handled by the existing facility
until at least 2018, this concept is being recommended
for quality of life issues for the local communities.
The SDRP discusses that people choose to live in Rural
Planning Area's because the community character is
compact, rural and often historic, as it is in Lafayette.
The Plan also discusses the need to protect the character
of existing, stable communities, but notes that planning
initiatives in these areas have not always promoted
rural character, and master plans include roads that
induce sprawl. In this case, even though the traffic
volumes in the future can be supported by the existing
facility, it is more traffic than Lafayette can handle
without detracting from its character. Web site replies
from Lafayette, garnered from the Community Assessment
used to understand each community's vision, talk about
its "rural character" and worry about its
"historic integrity". Residents have voiced
concerns about their quality of life both through
the web site and at the public meetings. The consensus
from our outreach is that the bypass is a concept
that is supported and encouraged, but a widening cannot
and should not be pursued.
This
area of the State is identified as Rural and Environmentally
Sensitive Planning Areas and part of the Highlands.
While it is important to maintain the integrity of
these environments, the viability of the local communities
must also be weighed. The Plan notes that while we
must encourage alternatives to driving alone, we need
to enhance a transportation system that limits scattered
and piecemeal development. The SDRP allows that traffic
for the seasonal demands of travel and tourism that
support recreational and natural resource-based activities
should be accommodated. The bypass concept, while
it will have impacts, at the same time strives to
meet the spirit of the plan. The concept is for the
bypass to be a two lane, limited access facility.
No development would occur along the bypass as there
would be no access. The viability of the town would
be preserved while removing the regional traffic from
its "main street". A limited access bypass
would protect the area from the "piecemeal development"
cited by the Plan while allowing for the demands of
recreational activities which helps support the local
economy.
Other
intersection improvement concepts at Sunset Inn Road
and Morris Farm/Meadows Road are not needed until
at least 2008 and 2018 respectively and did not receive
favorable comment at the public meetings. These improvements
will not be needed within the next twenty years if
the bypass is built.
While
the EIS will consider the possibility of an off-alignment
freeway between Rt. 181 and Rt. 94, the second concept
of a bypass from Rt. 94 to Rt. 206 has independent
utility from the proposed widening. Even if an alternate
alignment is the preferred solution between Rt. 181
and Rt. 94, there is a need for traffic to have access
at the junction of Route 94 which means that a separate
freeway alignment would have to tie into Route 94
and then proceed north. Regardless of the alignment
chosen south of Route 94, a bypass from the junction
at 15/94 to 206 is independent of the concept between
181 and 94.
Conclusion
This study presents several concepts to improve the
mobility and safety in the Route 15 corridor. As the
Department advances the concept solutions, some policy
level decisions need to be made regarding the different
situations and issues that are presented in the corridor.
Overall, the concepts are meant to provide reasonable
engineering solutions to very complex issues that fit
within the context or vision of the communities involved.
|
|