Stages
The project
design proposes five main
construction stages that
require sub stages. Ramps
will be closed and detoured at
specific locations as needed.
All dates are approximate
and subject to change.
The files below are
in Portable Document Format
(PDF). You will need Adobe
Acrobat Reader, which is
available free from the state
Adobe Access page, to
view the files.
Stage 3: mid
October 2010 to late Fall
2012
- Re-establish northbound
and southbound to three
lanes in each direction;
- Install permanent guiderails;
- Close lanes as needed
to allow for construction
of Intelligent Transportation
Systems (ITS) facilities;
- Full-depth concrete
pavement repairs along
the southbound roadway;
south of milepost 46.5
Stage 5: mid
September 2010 to mid October
2010- Completed
- Establish the normal
traffic pattern on the
north and southbound roadways
(two lanes in each direction);
- Close lanes as needed
to allow construction
of the final pavement
surface course (2" thick)
along 11 miles of the
northbound roadway; work
will start by mid September
and be completed by mid
October 2010;
- Close and detour the
northbound ramps (overnight)
at Interchanges 47, 52
and 56 while paving I-295
northbound through these
interchange areas;
- Remove emergency pull-offs
along the outside of the
northbound roadway.
Stage 4: early
August 2010 to mid September
2010 -
Completed
- Close and
detour the
southbound entrance ramp
at Interchange 57 and
establish interim I-295
traffic pattern, providing
two lanes
of traffic in each direction
traveling on the newly
reconstructed northbound
roadway separated by a
temporary concrete barrier
curb, with emergency pull-off
areas provided approximately
every half mile along
the outside;
- Southbound traffic will
be crossed over onto the
northbound roadway via
diversionary road
across the median at the
north end of the project
(near Interchange 57),
and crossed back over
onto the southbound
roadway via diversionary
road across the
median located approximately
one mile north of Interchange
45;
- Reconstruct approximately
11 miles of the I-295
southbound roadway and
ramps under an accelerated
schedule while maintaining
access to ramps on the
southbound side via
diversionary roads across
the median;
- Close and detour the
southbound ramps at reconstructed
interchanges sub-staged
as follows: 4a/Interchange
52; 4b/Interchange 56;
4c/Interchange 47, with
no two interchanges closed
at the same time;
- Construct a retaining
wall along the outside
of the widened southbound
roadway under the bridge
at Interchange 52;
- Construct/remove diversionary
roads as needed;
- Construct repairs to
southbound bridge decks,
deck joints, and approach
and transition slabs;
- Construct beam guide
rail and signage (predominantly
along the outside of the
southbound roadway);
- Remove emergency pull-offs
adjacent to southbound
shoulders.
Stages
4a, 4b and 4c maps for
Interchanges 45, 47, 52,
56 and 57
(pdf
1.45m)
Interim Stage:
early August 2010 - Completed
- Construct/remove diversionary
roads as needed;
- Move the movable concrete
barrier on I-295 northbound;
- Construct emergency
pull-offs adjacent to
both northbound shoulders;
- Traffic pattern for:
- I-295 northbound
- Two lanes will
be open. Traffic
will be on the outside
shoulder and outside
lane.
- I-295 southbound
- Two lanes will
be open. Traffic
will be on the outside
shoulder and outside
lane
Stage 2: mid
June 2010 to late July 2010
- Completed
- Close and detour the
northbound entrance ramps
at Interchange 45 and
establish interim I-295
traffic pattern providing
two lanes of traffic in
each direction using the
southbound roadway separated
by a temporary concrete
barrier curb, with emergency
pull-off areas provided
approximately every half
mile along the outside;
- Northbound traffic will
be crossed over onto the
southbound roadway via
a diversionary road across
the median at the south
end of the project (near
Interchange 45), and crossed
back over onto the northbound
roadway via a diversionary
road across the median
at the north end of the
project (near Interchange
57);
- Reconstruct 12 miles
of the I-295 northbound
roadway (less final surface
course) and ramps under
an accelerated schedule
while maintaining access
to ramps on the northbound
side via diversionary
roads across the median;
- Close and detour the
northbound ramps at reconstructed
interchanges sub-staged
as follows: 2a/Interchange
52; 2b/Interchange 56;
2c/Interchange 47, with
no two interchanges closed
at the same time;
- Complete construction
of unfinished underdrains/edge
drains along northbound
shoulder;
- Construct a retaining
wall along the outside
of the widened northbound
roadway under the bridge
at Interchange 52;
- Construct repairs to
northbound bridge decks,
deck joints, and approach
and transition slabs;
- Construct permanent
beam guide rail and signage
(predominantly along the
outside of the northbound
roadway);
- Construct temporary
guide rail along the outside
of the northbound roadway
(in preparation for the
Stage 4 traffic pattern).
Stages
2a, 2b and 2c maps for Interchanges
45, 47, 52, 56 and 57
(pdf
1.88m)
Stage 1: February
2010 to mid June 2010 - Completed
- Reconstruct both shoulders
(asphalt) to grade along
the southbound roadway
including underdrains/edge
drains;
- Reconstruct (full boxout)
the northbound roadway
in the vicinity of Interchange
57 and the I-295 northbound
exit ramp onto Route 130
at Interchange 57, which
will require the ramp
to be closed and detoured;
- Construct emergency
pull-offs adjacent to
both southbound shoulders;
- Reconstruct inlets along
the southbound shoulders
as required;
- Construct diversionary
roads (mainline and ramps),
permanent and temporary
drainage, and temporary
guide rail in the median;
- Perform clearing along
the northbound roadway;
- Construct underdrain/edge
drains along the northbound
shoulders in advance of
Stage 2 work if necessary
by the contractor
|