The traffic staging and work schedule is based on the most recent information provided by the contractor.
Through
June 2008 -
completed |
Work: |
- Construction of temporary North intersection
- Preparation work
for removal of south
half of existing bridge
|
Traffic: |
- No change to existing traffic patterns
|
|
|
June 2008 - Labor Day 2008 -
completed |
Work: |
- Removal of portion of the superstructure of the existing bridge
- Start of foundation work for new southbound bridge
- Start of pedestrian bridge piers for north pedestrian bridge
|
Traffic: |
- Maintain one lane of traffic in each direction on existing bridge
- Maintain ramp for Sandy Hook Park southbound traffic traveling to Ocean Avenue (Sea Bright) southbound
- Maintain exit ramp for Route 36 southbound bridge traffic traveling into Sandy Hook Park
|
|
|
Labor Day 2008 - May 1, 2009 -
completed |
Work: |
- Completion of foundations
for the new southbound
bridge
|
Traffic: |
- Maintain one lane of traffic in each direction on existing bridge
- Close ramp for Sandy Hook Park exiting traffic traveling to Ocean Avenue (Sea Bright) southbound
- Close exit ramp for Route 36 southbound bridge traffic traveling into Sandy Hook Park
- Close ramp for Sandy Hook Park exiting traffic traveling onto the Route 36 northbound bridge
NOTE: Closed ramp traffic movements are rerouted through new temporary North intersection |
|
|
May
1, 2009 - Labor Day
2009 -
completed |
Work: |
- Completion of
piers and superstructure
for the new southbound
bridge and south
pedestrian bridge
|
Traffic: |
- Maintain one lane of traffic in each direction on existing bridge
- Reopen ramp for Sandy Hook Park exiting traffic traveling onto the Route 36 northbound bridge
NOTE: North temporary intersection remains for Route 36 southbound entry into Sandy Hook Park. Southbound traffic exiting Sandy Hook Park will be detoured onto the bridge (Route 36 northbound) to Bay Avenue in Highlands and/or Scenic Drive in Atlantic Highlands, then back to Route 36 southbound bridge. |
|
|
Labor
Day 2009 - October 2009 -
completed |
Work: |
- Completion of
foundations, piers
and superstructure
for the new southbound
bridge and south
pedestrian bridge
- Construct South temporary intersection.
|
Traffic: |
- Maintain one lane of traffic in each direction on existing bridge
|
|
|
November
2009 - December 2009 -
completed |
Work: |
- Completion of the new ramp for Sandy Hook Park southbound traffic traveling to Ocean Avenue (Sea Bright) southbound
- Completion of new exit ramp for Route 36 southbound bridge traffic traveling into Sandy Hook Park
|
Traffic: |
- Open new southbound bridge
- Maintain one lane of traffic in each direction on new bridge
- Open ramp for
Sandy Hook Park
exiting traffic
traveling into Sea
Bright and traffic
from Route 36 southbound
traveling into Sandy
Hook Park
- Open ramp for
Sandy Hook Park
exiting traffic
traveling onto the
Route 36 northbound
bridge using new
south temporary
intersection
|
|
|
December
2009 -
December 2010 -
completed |
Work: |
- Demolition of north half of existing bridge followed by construction of the new northbound bridge
- Substantial completion
is anticipated for
December 16, 2010
|
Traffic: |
- Maintain one lane
of traffic in each
direction on new southbound
bridge
- Continue using
South temporary
intersection
- Continue using ramp
for Sandy Hook Park
exiting traffic
traveling to Ocean
Avenue (Sea Bright)
southbound
- Continue using ramp
for Route 36 southbound
bridge traffic traveling
into Sandy Hook
Park
|
|
|
January 2011 - May 2011 -
completed |
Work: |
- Final landscaping
- Project cleanup
- Final project acceptance work
- Project completion
is anticipated for
March 31, 2011
|
Traffic: |
- Open two lanes of traffic in each direction on new southbound and northbound structure
- Open ramp for
Sandy Hook Park
exiting traffic
traveling onto
Route 36 northbound
|