Stages and Schedule
Stage
1 A: June
2009 - March 2010 - Completed |
- Construct Duffield/St. Paul's
Avenues intersection
- Construct pre-loading at
west end of project between
Charlotte and Duffield
Avenues
- Begin construction of mainline
Viaduct over St. Paul's
Avenue and Loop
Ramp D
- Begin construction of Route
1&9T Flyover
Ramp
- Begin construction of the
Tonnele Avenue bridges
over NJ TRANSIT and Conrail
railroad tracks
Description
of Ramps:
Loop
Ramp D - Will
pass
over the Tonnele
Circle, pass under
Ramp I and the
mainline Route
1&9T
before tying into
Route 1&9T southbound
Route
1&9T Flyover Ramp - Will
extend from Route 1&9T
northbound passing over
Tonnele Avenue, NJ TRANSIT
and Conrail railroad
tracks and ends in the
area of Spruce Street |
Stage
1 B: March 2010
- October 2011 -
Completed |
- Construct Ramp
A bridge
- Continue construction of mainline
Viaduct over St. Paul's Avenue
and Loop
Ramp D
- Continue construction of Route
1&9T Flyover
Ramp
- Construct the crossover
ramp,
Ramp B and Ramp
G
- Construct and complete the Route
1&9T bridge over Charlotte
Avenue
- Construct Ramp H
- Continue construction of the
Tonnele Avenue bridges over
NJ TRANSIT and Conrail railroad
tracks
Description of
Ramps:
Ramp
A - Will connect Route
1&9T northbound and St. Paul's
and James Avenues to Route 7 westbound
Loop
Ramp D - Will pass over
the Tonnele Circle, pass under
Ramp I and the mainline Route
1&9T before tying into Route
1&9T southbound
Route
1&9T Flyover
Ramp - Will
extend from Route
1&9T
northbound passing
over Tonnele Avenue,
NJ TRANSIT and
Conrail railroad
tracks and ends
in the area of
Spruce Street
Crossover
Ramp - Will extend
eastward from Ramp A
to the split of Ramp
B and the mainline Route
1&9T
near Charlotte
Avenue
Ramp
B - Will exit
the mainline west of
Charlotte Avenue and
pass over Charlotte Avenue
and Ramp C, proceeding
toward the existing connection
at the Tonnele Circle
Ramp
G - Will
connect Route 1&9T southbound
with Charlotte Avenue
immediately north of
the Route 1&9T/Newark
Avenue intersection
Ramp
H - Route 1&9T
southbound ramp that
will connect the Tonnele
Avenue bridge over NJ
TRANSIT to the mainline
Viaduct over St. Paul's
Avenue |
Stage
1 C: July
2010 - February 2011-
Completed |
- Shift Charlotte Avenue southbound
traffic to the Charlotte
Avenue southbound ramp
- Open Ramp A for Route 7 westbound
traffic from St. Paul's Avenue
only
- Construct the Route 1&9T mainline
over Charlotte Avenue
- Connect Ramp
G from Route
1&9T mainline over Charlotte
Avenue to the Charlotte Avenue
southbound ramp
- Continue superstructure construction
of bridges Ramp
B, Ramp C and Route 1&9T mainline Viaduct
- Construct Ramp
H, between
Tonnele Avenue and the Route
1&9T southbound Viaduct
- Construct the western remainder
of the Tonnele Avenue bridges
over NJ TRANSIT and Conrail
railroad tracks
- Modify the interim traffic
signal system at Tonnele
Circle
- Construct the piers of the
Route 1&9T Flyover Ramp adjacent
to the proposed westerly
curbline of Tonnele Avenue
Description
of Ramps:
Ramp
A - Will connect Route
1&9T northbound and St.
Paul's and James Avenues to
Route 7 westbound
Ramp G - Will
connect Route 1&9T southbound
with Charlotte Avenue immediately
north of the Route 1&9T/Newark
Avenue intersection
Ramp B - Will
exit the mainline west of Charlotte
Avenue and pass over Charlotte
Avenue and Ramp C, proceeding
toward the existing connection
at the Tonnele Circle
Ramp C - Will
extend from Charlotte Avenue
to the mainline Viaduct, this
ramp will replace the connection
to the existing Viaduct by
collecting the traffic from
Route 1&9T northbound and
from Route 7 eastbound
Ramp H - Route
1&9T southbound ramp that
will connect the Tonnele Avenue
bridge over NJ TRANSIT to the
mainline Viaduct over St. Paul's
Avenue
Route 1&9T
Flyover Ramp - Will extend
from Route 1&9T northbound
passing over Tonnele Avenue,
NJ TRANSIT and Conrail railroad
tracks and ends in the area of
Spruce Street |
Stage
1 D: February
2011 - July 2011 -
Completed |
- Continue construction
of the northbound and southbound
Viaducts and the Ramp
C and Ramp
B Viaducts
- Complete construction
of the Route 1&9T mainline
bridge over Charlotte
Avenue
- Divert southbound Tonnele
Avenue traffic from its
Stage 1C location to the
Stage 1D location along
the west curbline
- Construct the proposed
median barrier of Tonnele
Avenue and proposed Route
1&9T Flyover Ramp piers
- Shift Route 1&9T southbound
and Route 7 traffic to
the new Route 1&9T southbound
Description
of Ramps:
Ramp
C - Will extend
from Charlotte Avenue
to the mainline Viaduct,
this ramp will replace
the connection to the
existing Viaduct by collecting
the traffic from Route
1&9T northbound and
from Route 7 eastbound
Ramp
B - Will exit
the mainline west of
Charlotte Avenue and
pass over Charlotte Avenue
and Ramp C, proceeding
toward the existing connection
at the Tonnele Circle
Route
1&9T Flyover Ramp
- Will extend
from Route 1&9T northbound
passing over Tonnele
Avenue, NJ TRANSIT and
Conrail railroad tracks
and ends in the area
of Spruce Street
|
Stage
2 A: April
2010 - October 2011 -
Completed |
- Complete construction
of Ramp
C between Ramp
B bridge and the Tonnele
Circle
- Complete construction
of mainline Viaduct over
St. Paul's Avenue and Loop
Ramp D
- Complete construction
of Route
1&9T Flyover
Ramp
- Complete construction
of the Tonnele Avenue bridges
over NJ TRANSIT and Conrail railroad
tracks
Description
of Ramps:
Ramp
C - Will extend from
Charlotte Avenue to the mainline
Viaduct, this ramp will
replace the connection to
the existing Viaduct by collecting
the traffic from Route 1&9T
northbound and from Route
7 eastbound
Ramp
B - Will exit the
mainline west of Charlotte
Avenue and pass over Charlotte
Avenue and Ramp C, proceeding
toward the existing connection
at the Tonnele Circle
Loop
Ramp D - Will pass
over the Tonnele Circle,
pass under Ramp I and the
mainline Route 1&9T before
tying into Route 1&9T southbound
Route 1&9T
Flyover Ramp - Will extend
from Route 1&9T northbound
passing over Tonnele Avenue,
NJ TRANSIT and Conrail railroad
tracks and ends in the area of
Spruce Street |
Stage
2 B: October
2011 - March 2012 -
Completed |
- Shift Route 1&9T southbound
and Route 7 traffic to the
new Route 1&9T southbound
- Shift Route 1&9T northbound
and Route 7 traffic to the
new mainline Viaduct and
the Route
1&9T Flyover Ramp
- Close the St. Paul's Avenue
Viaduct westbound to traffic
- Begin construction of the
reconfigured Tonnele Circle
Description
of Ramps:
Route 1&9T Flyover
Ramp - Will extend from Route
1&9T
northbound passing over Tonnele Avenue,
NJ TRANSIT and Conrail railroad tracks
and ends in the area of Spruce Street |
Stage
3 A: March
2012 - October 2012 -
Completed |
- Close existing access from the
Tonnele Circle to the Pulaski
Skyway
- Begin construction of Ramp
I bridge over Ramp
D
- Begin construction of Ramp
D bridge over the Tonnele Circle
- Complete construction of Ramp
B bridge over Charlotte
Avenue and Ramp C
- Complete construction of Ramp
C construction at Charlotte
Avenue
- Complete demolition of existing
Viaduct
- Construct connection of Ramp
B Viaduct to the Ramps
B/C approach to
Tonnele Avenue
Description of
Ramps:
Ramp
I - Will cross over Loop
Ramp D and the combined Ramp
B/C before tying into the existing
Pulaski Skyway westbound lanes,
this ramp will replace the existing
ramp
Ramp D - Will pass over
the Tonnele Circle, pass under Ramp I
and the mainline Route 1&9T before
tying into Route 1&9T southbound
Ramp
B - Will exit
the mainline west of
Charlotte Avenue and
pass over Charlotte Avenue
and Ramp C, proceeding
toward the existing connection
at the Tonnele Circle
Ramp
C - Will extend
from Charlotte Avenue
to the mainline Viaduct,
this ramp will replace
the connection to the
existing Viaduct by collecting
the traffic from Route 1&9T
northbound and from Route
7 eastbound |
Stage
3 B: July
2012 - October 2012 -
Completed |
- Construct Ramp
E between St.
Paul's Avenue and Ramp
D
- Complete construction of Ramp
I bridge over Ramp
D
- Open access from southbound
Tonnele Avenue to the Pulaski
Skyway
- Complete construction of Ramp
D bridge over the Tonnele
Circle
Description of
Ramps:
Ramp
E - Will extend northward
from St. Paul's Avenue to Ramp
D, providing access to mainline
Route 1&9T
Ramp D - Will pass over the Tonnele
Circle, pass under Ramp I and the mainline
Route 1&9T before tying into Route
1&9T southbound
Ramp I - Will
cross over Loop Ramp D and the combined
Ramp B/C before tying into the existing
Pulaski Skyway westbound lanes, this
ramp will replace the existing ramp |
Stage
3 C: November
2012 - January 2013 -
Completed |
- Complete construction of the
reconfigured Tonnele Circle
- Open access from the Tonnele
Circle to the Pulaski Skyway
|
|
|