Rt 206 Doctors Way to Valley Road project

Hillsborough, Somerset County
Last Update: October 24, 2024

Construction to widen Route 206 within the project limits to two travel lanes in each direction has resumed after a lengthy pause while the services of a new contractor were obtained.

The project begins south of the Doctors Way intersection (Milepost 66.36) and ends approximately one half mile north of the Valley Road intersection (Milepost 68.00).

Scheduled Completion: Fall 2026


Project Details

The $42 million contract includes construction of multiple operational, safety and state-of-good-repair improvements for all highway users.

  • Widening the highway to two travel lanes in each direction, divided by a center median concrete barrier
  • Constructing jughandles for U-Turn movements at Triangle Road, Valley Road, and near Camplain Road
  • Realigning the highway throughout the project limits
  • Regrading Falcon Road to match new grades of Rt 206. Falcon Road will be temporarily closed and detoured. The detour will utilize Opie Road and will not affect traffic on Route 206.
  • Replacing a culvert on Route 206 near Valley Road and building a new bridge over a tributary to Royce Brook to connect Valley Road to Route 206
  • Creating drainage basins within the new jughandles and at other locations
  • Upgrading lighting throughout the project limits
  • Upgrading traffic and pedestrian signals throughout the project limits
  • A noise wall (completed) along Rt 206 southbound between Farm Road and Doctors Way


Construction of footing for the replacement of Valley Road Bridge
Work in Progress

Construction of footing for the replacement of Valley Road Bridge.





Construction of jughandles
Work in Progress

Construction of jughandles at the northern limit of the project will provide Rt 206 northbound and southbound motorists with U-turn and left-turn movements. Photo depicts work on the jughandle for Rt 206 northbound motorists.




Project Milestones

Construction Activity Status Estimated Start/Finish
Noise Wall Complete May 2022
Jughandles In Progress Finish: Winter 2025
Culvert & Bridge replacement In Progress Finish: Spring 2025
Drainage system In Progress Finish: Summer 2025
Curb and Sidewalk In Progress Finish: Summer 2025
Stage 1: widening northbound side of Rt 206 In Progress Finish: Fall 2025
Upgraded traffic & pedestrian signals Not Yet Started Start: Fall 2024
Regrading Falcon Road Not Yet Started Start: Spring 2025
Upgraded Lighting Not Yet Started Start: Spring 2025
Stage 2: widening southbound side of Rt 206 Not Yet Started Start: Fall 2025
Stage 3: median barrier and final paving Not Yet Started Start: Spring 2026
Project completion In Progress Finish: Fall 2026




Construction of jughandles
Project location map

Google Earth

Last updated date: October 24, 2024 2:23 PM