April 2005
The segments for the last approach span are being pulled together with post tensioning bars. When the span is complete, these temporary bars will be removed. This work was completed on April 11, 2005. |
|
April 2005
The employees of George Harms Construction, Inc. pause for a picture on April 11, 2005 before placing the last pre-cast segment on the project. |
|
April 2005
Another milestone was achieved on April 11, 2005 as the last superstructure segment is erected. The segment is being guided into position by the crew to complete the span. |
|
April 2005
The completed southbound structure of the Victory Bridge taken on April 11, 2005. The structure has carried north and south bound traffic across the Raritan River since opening on June 8, 2004. |
|
|
|