Schedule

Anticipated Construction Timeline Key Work Primary Responsible Party
Phase 1

January – March 2018
Replacing signs in New Jersey starting at existing I-95 interchange 8/Princeton Pike and moving west toward the Delaware River NJDOT
Phase 2

March - April 2018
Replacing signs on both sides of the Delaware River within the Scudders Fall Bridge project limits (existing
I-95 Exit 1 in New Jersey and Exits 51 and 49 in Pennsylvania).
DRJTBC/ PennDOT/PTC
Phase 3

April – August 2018
Replacing signs at the remaining interchanges through the new interchange in Bristol, PA. PTC/PennDOT/ NJTA