Q. |
Why
is this work necessary? |
A: |
A segment
of Route 35 on the
Barnegat Peninsula
in Ocean County was
severely compromised
as a result of Superstorm
Sandy on October
29, 2012. The New
Jersey Department of
Transportation (NJDOT)
took immediate steps
after the storm to
restore safe travel
on the highway, but
a complete reconstruction
is required.
The Department is
moving swiftly to substantially
complete the project
in a period of two
years – by the summer
of 2015 – to minimize
the risk of losing
use of this vital highway
from damage inflicted
by a future storm.
A less extensive project
had been planned to
rehabilitate Route
35 later this decade,
but the damage caused
by Superstorm Sandy
prompted the Christie
Administration to accelerate
and augment those plans
to the present.
|
|
|
Q. |
What
is being done under
this project? |
A: |
A 12.5-mile segment
of Route 35 on the
Barnegat Peninsula
is being completely
rebuilt. This $341 million federal- and
state-funded project
includes the construction
of a stronger, more
resilient roadway,
a new drainage system
that will significantly
improve the stormwater
drainage characteristics
of the highway, and Complete
Streets features
to improve safety for
pedestrians and bicyclists. |
|
|
Q. |
Where
is the work being
performed?
|
A: |
The
project area extends
12.5 miles through
eight municipalities
along the Barnegat
Peninsula from Milepost
(MP) 0.0 in Berkeley
to MP 12.5
in Bay Head. From south
to north, the project
passes through Berkeley,
Seaside Park, Seaside
Heights, Toms River,
Lavallette, another
section of Toms River,
Brick, Mantoloking
and Bay Head.
Work will be performed
along the highway
and at locations
close to the bay, which include both gravity outfalls and
pump stations for the
new drainage system. Temporary
trenches will be dug
along local streets
for pipes connecting
the drainage system
along Route 35 to the
pump stations.
A total of nine underground
pump stations will
be built. Each will
be accompanied by an
electrical and control
panel elevated above
the ground to protect
the equipment from
floods. Pump locations:
- Berkeley – One
pump station at
Bayview and 22nd
avenues
- Seaside
Park – Three pump
stations at Bayview
and 8th avenues,
Bayview and Island
avenues, and on L
Street
- Toms
River – One pump
station on Eisenhower
Avenue
- Mantoloking – Two
pump stations on
Lyman Street and
on Downer Avenue
- Bay Head – Two
pump stations on Goetze
Street and on Mount
street
|
|
|
Q. |
How
will traffic be handled
during construction,
and when can I expect
lane closures? |
A: |
As of June 2015, all Route 35 travel lanes
for the entire 12.5 miles are now open. Short duration traffic shifts or lane closures may be necessary for installing vehicle detection and doing some limited work on shoulders, sidewalks, crosswalks, curbs and landscaping items. |
|
|
Q. |
Will
access to my property
be affected? |
A: |
Yes.
When construction activity
takes place in front
of driveways, access
will be affected. Notice
will be given to homeowners
prior to work that
blocks access, and
access will be restored
within 18 days. |
|
|
Q. |
What
if I need access to
my driveway during
a period of no access? |
A: |
If
special circumstances
arise, contact the
Department's community
outreach team. |
|
|
Q. |
Will
my mail delivery be
affected? |
A: |
Yes.
Mail delivery will
be affected at various
times, such as when
construction activity
blocks access for letter
carriers. The Department
is working to create
temporary delivery
locations. |
|
|
Q. |
Will
my utility service
be interrupted? |
A: |
Yes.
There will be times
of service disruptions
depending on the needs
of utility companies
to repair or replace
lines. Utility companies
or NJDOT's Community
Outreach Team will
notify residents. |
|
|
Q. |
Will
the work require detours
of traffic onto local
streets? |
A: |
Generally,
no. The only exception
is a section of Route
35 between 14th and
20th avenues in Berkeley
Township. |
|
|
Q. |
When
does construction start? |
A: |
Work began at the end of August 2013. The
project has been divided
into three
geographic areas, with three separate
contractors performing
the work. The contractors
are allowed to work on
pump stations and other
project elements that
will not reduce the normal
complement of Route 35
travel lanes during the
high-traffic-volume summer
months (June through
Labor Day). Work that
requires Route 35 lane
closures will be restricted
to non-summer months,
when traffic volumes
are significantly lower.
The project sections,
delineated by MP are:
- MP
0.0 to 4.0:
Berkeley, Seaside
Park, Seaside Heights
and Toms River
- MP
4.0 to MP 9.0:
Lavallette, Toms
River and Brick
- MP
9.0 to MP 12.5:
Mantoloking and
Bay Head
|
|
|
Q. |
When
will the project be
completed? |
A: |
Contract 3, MP
0.0 to 4.0:
(Berkeley, Seaside
Park, Seaside Heights
and Toms River)
As of June 2015, the final pavement for Route 35 has been completed, including vehicular and bicycle lane striping, with all Route 35 travel lanes open. All sidewalk and pedestrian facilities have been installed. Minor corrective work is ongoing. All drainage outfalls and pump stations have been installed. All travel lanes are open with exception of temporary lane closures which will be utilized for minor sidewalk and pedestrian facility work. Landscaping in the vicinity of the pump stations will be completed this Fall.
Contract 2, MP
4.0 to MP 9.0:
(Lavallette, Toms
River and Brick)
As of June 2015,
all Route 35 travel lanes are open with shoulder closures being necessary for work zones in select locations. Sidewalks and pedestrian facility work are continuing. All drainage outfalls have been installed. All work is expected to be completed this Fall.
Contract 1, MP
9.0 to MP 12.5:
(Mantoloking and
Bay Head)
As of June 2015, the final pavement for Route 35 has been completed. Lane striping and bicycle accommodations have been completed. All sidewalk and pedestrian facilities have been installed. Miscellaneous landscaping work continues throughout the project limits. All drainage outfalls and pump stations have been installed with minor work in progress for the Mount Street pump station, which is expected to be completed this Fall. All Route 35 travel lanes are open for the Summer 2015 season. Short duration traffic shifts are expected when vehicle detectors are installed at signalized intersections. |
|
Q. |
How
will motorists be notified
when work on certain
parts of Route 35 affect
their daily commute? |
A: |
NJDOT
will use Variable Message
Signs (VMS), newspapers,
radio, traffic reports
and its web site to
alert motorists. |
|
|
Q. |
Will
pedestrian routes be
affected by construction? |
A: |
Yes.
However, temporary
alternative pedestrian
routes will be provided. |
|
|
Q. |
How
is emergency access
being addressed throughout
the Route 35 project
area? |
A: |
A single
lane along Route 35
will always be provided. |
|
|
Q. |
What
Complete Streets improvements
will benefit pedestrians
and bicyclists? |
A: |
The
reconstruction of Route
35 will include Complete
Streets features
such as sidewalks,
bicycle compatible
roadway shoulders and
Americans with Disabilities
Act-compliant (ADA)
ramps will be built
where there is sufficient
NJDOT right of way.
Pedestrians
and bicyclists can
expect the following
improvements:
- Virtually continuous
sidewalk will be
constructed along
the entire length
of Route 35 northbound.
The project includes
63,000 linear feet
of new or rebuilt
sidewalk.
- High visibility
crosswalks will be
created throughout
the corridor to guide
pedestrians to designated
crossing locations
and to alert motorists
where to expect pedestrian
crossings to take
place. Crosswalks
will be equipped
with 200 new pedestrian
countdown heads.
- Approximately1,200
ADA ramps will be
installed at intersections.
- Efforts will
be made to accommodate
bicyclists through
the creation of designated
bike lanes
where feasible. Striping
and signage will
be installed to help
bicyclists and motorists
share the road safely.
- Improvements to
the streetscape and
median areas will
make the area more
inviting and comfortable
for those walking
or biking along the
corridor.
|
|
|
Q. |
How
will construction activity
affect traffic on local
streets? |
A: |
Work within
the business districts
will be limited to block-by-block
staging to minimize impacts
to businesses and parking.
Local street impacts
will be limited to those
streets which will accommodate
drainage pipes routed
to Barnegat Bay outfalls. |
|
|
Q. |
How
will the reconstruction
address flooding and
stormwater pollution? |
A: |
An all-new
underground stormwater
drainage system will
be installed, including
an increased number of
inlets to collect roadway
runoff. Water quality
chambers will be installed
on each outfall to improve
the quality of water
discharged into the Barnegat
Bay. The system is designed
to handle drainage needs
of Route 35, not local
streets. |
|
|
Q. |
How
is the roadway being
redesigned to be able
to handle another storm
like Sandy? |
A: |
The 8-inch-thick
concrete or asphalt roadway
will be replaced with
24-inch-thick roadway
engineered for stability
and strength. |
|
|
Q. |
How
can I stay informed or comment on
this project? |
A: |
NJDOT
encourages community
members to submit comments
to the Project Outreach
Team at:
-
E-mail
- Phone:
732.230.7356
This
hotline will be available
at all times for
residents or others
to leave messages
that will be returned
by the outreach team.
|
|
|