September
2007
At a Community Liaison Committee
(CLC) meeting held in September 2007,
members received further updates on the
project. Examples of clear noise walls
were presented to the group. It was noted
that as a result of the Smart Solution
Alternative, the Route 3 roadway profile
has been revised. Due to that change
in design, the noise wall calculations
have changed and need to be redesigned
and be run through a model to obtain
final dimensions. Also presented was
information regarding interim repairs
to the Route 3 Bridge over the Passaic
River, which began on Monday, September
24, 2007; sidewalk and streetscape designs
on Park Avenue; construction schedule
information; as well as updates being
made to this project web site.
Comments on the work
of the CLC or any other
aspect of the project
can be made by calling
the Route 3 project information
line at 1-866-FX
RT 3/21 (1-866-397-8321)
or by sending an e-mail
to the Project Team via
the comments section.
As the project moves forward, the CLC
will continue to assist the New Jersey
Department of Transportation (NJDOT)
in building consensus on other key
decisions for this regionally significant
project.
June
2007
A CLC meeting was held in June 2007 to
provide updates on the project's status,
to explain the Smart Solution Alternative
and to provide updates on resolutions
from the affected communities on the
issue of noise walls. Many concerns were
raised about lane configurations and
the management of traffic flow along
Route 3, as well as traffic monitoring
and motorists notification during construction.
In addition, an inquiry was made about
providing a designated lane for buses
and other high occupancy vehicles (HOVs).
It was explained that sufficient space
does not exist within the existing right
of way to accommodate a bus lane. However,
an HOV lane may be possible, although
there is a concern that taking a lane
away from the general traffic use could
have a significant impact on traffic
flow in the other lanes.
June
and August 2004
CLC meetings were held in June 2004 and
August 2004 to discuss the architectural
treatments for the new bridge over the
Passaic River, the noise study and proposed
noise walls and preparation for the Public
Involvement Centers scheduled for October.
There was much discussion about noise
walls and how best to educate the communities
so that the public can make an informed
decision as to whether or not they want
the noise walls constructed. Several
displays and presentations were discussed
that would assist with the educational
process. It was decided that a brochure
would be prepared by the design team
including a questionnaire that will gauge
resistance or support for the noise walls.
Members of the committee made suggestions
for wording of the questionnaire. Responses
to these questionnaires will be collated
and summarized and presented to the municipalities.
Each municipality passed a resolution
in favor of the noise walls for this
project.
July
2002
At the following CLC meeting, held in
July 2002, NJDOT representatives presented
responses to additional points raised
by residents at the Borough's follow-up
meetings, further clarifying the decision-making
process for the ramp's geometry. The
CLC discussed additional refinements
to address the concerns where appropriate,
and the Design Team concurred that they
could be implemented. The CLC decided
that sufficient attention had been given
to addressing concerns of residents of
the Preble Place neighborhood, and that
it was now time to present the Preferred
Alternative - which shows the CLC's
Final Preferred Ramp Alternative -
to a broader audience, i.e. all project
area residents and other interested stakeholders.
As a result of this decision, and in
compliance with the NEPA process, NJDOT
scheduled public
information centers and public hearings to
hear community input on the project as
a whole. Prior to each of these meetings,
special Public Information Centers were
held in an open-house format to disseminate
information on the results of the project's
environmental investigations and conceptual
presentations on noise mitigation and
aesthetics.
June
2002
In May 2002, the Rutherford
Borough Mayor and the
Borough Engineer met
with residents of the
Preble Place neighborhood
and members of the Route
3 Impact Group, a coalition
of local residents who
share concerns about
the project. At the following
CLC meeting, held in June 2002, NJDOT
representatives responded point-by-point
to the residents' concerns, showing which
of the suggestions would be incorporated,
and explaining why some ideas could not
feasibly be implemented. A Route 3 Impact
Group member who was invited to the June
CLC meeting and later agreed to serve
as a CLC member, expressed appreciation
for the Project Team's comprehensive
response to the residents' suggestions.
He commented that the discussion represented "a
good give-and-take" between the community
and NJDOT.
After the June 2002 CLC meeting, the
Borough of Rutherford held two follow-up
meetings with neighborhood residents
and Impact Group members to review NJDOT's
responses to the most recent set of community
comments. One of these meetings was held
at the site of the proposed ramp, where
the Borough Engineer and residents could
refer to actual locations of ramp aspects
in question.
March
2002
Residents of Preble Place were invited
to meet with the CLC in March 2002 to
comment on the CLC's preferred ramp alternative.
After listening to neighborhood residents'
input, the CLC at its April meeting unanimously
endorsed the new ramp configuration as
a better alternative in terms of neighborhood
safety.
At the suggestion of the CLC, NJDOT installed
a large display showing both the originally
Initial Preferred Ramp Alternative and
the CLC's Initial Preferred Ramp Alternative
- and listing the advantages and disadvantages
of each - at Rutherford Borough Hall.
The exhibit was displayed from April
through June 2002, and the information
was also made available on handouts distributed
at Rutherford Borough Hall.
January
2002
At the first CLC meeting in January
2002, committee members shared their
concerns about neighborhood safety, particularly
in the area near the proposed Rutherford
westbound ramp. The following month,
the NJDOT Project Team presented the
CLC with a series of alternate ramp configurations,
one of which was chosen by the CLC members
for further study. During subsequent
meetings, the CLC and their constituents
provided input that resulted in the CLC's
initial preferred ramp alternative.