Bridge Profile:
The roadway
vertical
profile where the roadway
crosses a bridge. Survey
is used to assure that
beam bearings are set to
the proper elevation, so
that beams and decks provide
the proper riding surface
elevations when constructed.
Collector-Distributor
(CD) Roads:
A safe means of entering
and exiting into the main
traffic flow for major
routes like Route 3.
Constructability Review:
An evaluation of proposed
construction documents
to verify that the project
can be built safely as
shown, traffic can be maintained
during construction, and
the purpose and needs of
the project are met.
Contract Documents:
Plans and specifications
which direct the contractor
as to how to construct
the project.
Environmental Assessment:
A study to determine site
conditions such as historic
structures, hazardous materials,
archaeological sites, wetlands,
environmental justice issues,
and the effect of construction
on them. Mitigation measures
and obtaining permits are
addressed during final
design.
Feasibility Assessment
Study:
A study to assess the practicality
of certain alternative
designs.
Final Scope Development:
The refinement of the
Initial
Preferred Alternative (IPA) based
upon environmental studies,
community input and the
needs of the traveling
public.
Geotechnical:
The application of geology
to engineering; in this
case the support of structures
and roadways.
Initial Preferred Alternative
(IPA):
IPA is the proposed roadway
configuration identified
during the Feasibility
Assessment Review as being
best suited for study during
the Final Scope Development
Stage.
Low Level Photography:
Low Level Photography is
aerial photography taken
at a relatively low altitude
to obtain detailed mapping
information.
North Jersey Transportation
Planning Authority (NJTPA):
NJTPA is
the agency coordinating
transportation needs for
the region.
Office of Community
Relations (OCR):
New Jersey Department of
Transportation (NJDOT)
bureau acting as liaison
to local officials and
citizens to learn and address
their concerns.
Partnering Meetings:
Partnering is a project
management system designed
to lower costs and improve
communication. From the
initial partnering session
to project closeout, meetings
focus on the project itself
and related issues at hand.
The intent is to ensure
that the business processes
work as smoothly as possible,
with the focus on the project
itself. Participants typically
include NJDOT, New Jersey
Department of Environmental
Protection (NJDEP), governmental
agencies, local public
officials, utility companies,
mass transit agencies,
and Chambers of Commerce.
Project-specific web
site:
A web site devoted to a
specific NJDOT project.
Resolution of Support:
A formal proclamation issued
by the local governing
body; it endorses the Project
and requests the construction
of noise walls as part
of the Project. Clifton,
Lyndhurst, and Rutherford
have enacted Resolutions
of Support.
Right
of Way:
The land required to construct
the project, provide
wetlands
mitigation, and provide
access to adjacent properties
if necessary.
Scoping Process:
The
Final
Scope Development Stage
where the
IPA is
refined and environmental
issues are investigated
to determine if the approach
is viable.
Smart Solution Alternative:
Alternative involving significant
revisions to the project's
scope, schedule, construction
costs and project configuration
derived during the project's
preliminary design phase.
The goal of the smart solution
approach is to reduce cost
while fulfilling the project
needs. The project was
split into smaller components
to distribute costs over
a longer time period and
receive more competitive
bidding.
Technical Environmental
Studies:
Analysis of the effect
of the project on air and
noise quality, architectural
and archaeological features,
wetlands, parkland, and
adjacent property owners.
Topographical Mapping:
Topographical Mapping is
a precise detailed mapping
of the ground surface and
its features with regard
to vertical and horizontal
location.
Vertical Profile:
The mathematical line representing
the riding surface of a
roadway. This line is part
of the Contract Documents
and is established in the
field by survey through
an initial layout. Survey
control during construction
is provided to assure that
the final conditions are
in accordance with plans.
Wetlands Mitigation:
Measures such as the purchase
of land that can be converted
to wetlands which compensate
for acquisition of wetlands
areas need for construction
Right
of Way or easements.