Q. |
Why
is this work necessary? |
A. |
Due
to the deteriorated
condition of the
bridge superstructure
over the Passaic
River, the bridge
requires frequent
repairs. Because
of this, the bridge
over the Passaic
River requires replacement.
The bridge was originally
designed for two
traffic lanes in
each direction and
1940's vehicle loads.
As traffic volumes
increased, the shoulder
lanes on the bridge
were eliminated to
add an extra through
lane while providing
ramp access from
Route 21 and Riverside
Avenue. This ramp
access is now inadequate.
Heavy traffic volume during peak periods
combined with the inadequate or nonexistent
acceleration and deceleration lanes and
shoulders causes variable speeds and
sudden stops contributing to driver uncertainty.
Accident analysis and field observations
indicate a major problem for vehicles
at all the ramp locations within the
study area. Additional ramp acceleration/deceleration
lanes are required.
|
|
|
Q. |
What
is the schedule? |
A. |
The
project
schedule is:
Topographic
Survey |
Summer
2001 |
Community
outreach |
Ongoing
since Summer 2001 |
Finalize
the Final Scope
Development Package |
Spring
2003 |
Begin
Preliminary Design
Phase |
Spring
2004 |
End
Preliminary Design
Phase |
Spring
2005 |
Begin
Final Design Phase |
Spring
2007 |
Acquire
Kingsland Avenue
properties |
Spring
2007 |
Award
Kingsland Avenue
Demolition Contract |
Winter
2008 |
Award
Park Avenue Bridge
over Route 3 Contract |
Summer
2008 |
Substantial
completion of Park
Avenue Bridge over
Route 3 construction |
Spring
2010 |
Award
Route 3 over the
Passaic River Contract |
Summer 2010 |
|
|
|
Q. |
What
part of Route 3 will
be affected? |
A. |
The affected
area of Route 3 is
from Main Avenue in
Clifton to the Route
17 interchange in Lyndhurst
and Rutherford located
in Passaic and Bergen
counties. |
|
|
Q. |
Does
the New Jersey Department
of Transportation (NJDOT)
plan to widen Route
3? |
A. |
There
are no additional through
lanes within the project
limits. However, the
project as it is currently
proposed provides safety
improvements, including
new shoulders, auxiliary
lanes and acceleration/deceleration
lanes, as well as re-configured
exit ramps. This work
will be completed within
the existing Right
of Way of the current
roadway. The proposed
replacement of the
Route 3 Bridge over
the Passaic River will
be wider than the current
structure to accommodate
separated acceleration/deceleration
lanes. The project
is intended to improve
safety and help traffic
move smoothly along
Route 3, and is not
expected to add volume
to the roadway. |
|
|
Q. |
How
was the project's design
finalized? |
A. |
The
final design
was modified
to prevent or mitigate
any negative impacts
of the project. Community
input played a key
role in this process.
The NJDOT Project
Team provided
a comprehensive outreach
program so that impacts
were addressed
in partnership with
local communities.
The program addressed
the appearance of
the noise barriers
in conformance with
the Resolution
of Support. |
|
|
Q. |
Why
was the project smart
sized? |
A. |
The
project in its
Preliminary Design
Phase was deemed
very expensive.
Due to funding
issues, NJDOT made
major design changes
to smart size this
and several other
large projects.
The project was
split into smaller
components to distribute
costs over a longer
time period and
receive more competitive
bidding. The "smart
sizing" of the
project as originally
approved in the Preliminary
Design Phase has
resulted in a cost
savings of approximately
$60 million. |
|
|
Q. |
How
can I comment on this
project? |
A. |
NJDOT
encourages community
members to submit
comments to:
Deborah Hirt, Regional Manager
Office of Community Relations
New Jersey Department of Transportation
1035 Parkway Avenue
Trenton, NJ 08625
Phone: 609.530.2110
E-mail
|
|
|
Q. |
When
will construction begin
and when will it be
completed? |
A. |
Construction
will begin in
2010 and be completed
in stages in order to minimize
construction impacts
on the community
and expedite construction. |
|
|
Q. |
How
much will it cost and
who will pay for it? |
A. |
The
estimated cost
of this project
is under $200 million.
Federal funds are
being used for
this project. |
|
|
Q. |
Will
Route 3 be closed during
construction? |
A. |
No.
Three (3)
lanes of traffic
will be maintained
on Route 3 in each
direction during
the peak traffic
periods (AM and
PM rush hours)
throughout the
construction process.
|
|
|
Q. |
How
will motorists be notified
when work on certain
parts of Route 3 affect
their daily commute? |
A. |
Permanent
Dynamic Message
Signs (DMS) have
been installed
on the eastbound
side of Route 3
near Route 7 and
the westbound side
by Meadowlands
Parkway, which
will notify motorists
of delays and/or
construction impacts.
These will be supplemented
by mobile signage
to alert local
motorists of construction.
In addition, NJDOT
will use radio,
traffic reports
and its 511NJ
Travel Information
web site to alert motorists.
|
|
|
Q. |
What
will the area look
like when the work
is completed? |
A. |
The map
shows the proposed
improvements.
|
|
|
Q. |
What
are the environmental
elements? |
A. |
Environmental
issues that have
influenced the
design include
wetlands, noise
and air quality,
possible hazardous
materials in adjacent
land or water,
archaeology, historic
buildings or structures
and socioeconomic
considerations.
- Socioeconomics,
land use and
environmental
justice impacts
were investigated
for the two
industrial,
one commercial
and 15 residential
properties
impacted.
- Air and noise
studies concentrate
on sensitive
receptors,
such as residential
properties
in Rutherford
and Lyndhurst,
where noise
levels need
to be addressed.
- Feasibility
studies and
public meetings
have resulted
in a Resolution
of Support for
noise barriers
with architectural
enhancement
along Rutherford
Avenue and
Marginal Road,
Thomas E. Dunn
Highway, and
Route 3 in
Clifton.
- The archeologist/architectural
historian conducted
background
research to
establish eligible
cultural resources,
architectural
resources,
and recreational
land in the
project area.
- The ecological
study evaluated
existing ecosystems
and assessed
potential impacts.
Several wetland,
surface and
groundwater
studies have
recently been
conducted in
the area. The
existing information
was used to
assess the
potential impacts
of contamination
of natural
resources prior
to the project
start.
- A hazardous
waste screening
study was conducted
to assess potential
impacts associated
with the acquisition
of the Classic
Sanitation
property. Additionally,
potential impacts,
due to the
proximity of
numerous other
known contaminated
sites and possible
leaking Underground
Storage Tanks
(UST) sites,
as well as
the NJ TRANSIT
rail line were
assessed.
- Of particular
concern for
the project
is the quality
of the Passaic
River sediments
and the dewatering
effluent that
may have to
be managed
during construction.
A Waterfront
Development
Permit was
obtained for
the tidal Passaic
River.
- A very comprehensive
public involvement
program has
been developed
and implemented
to provide
the opportunity
for input from
the three affected
communities
located along
this section
of the roadway.
Copies of the
Environmental
Assessment were
distributed to
the public, various
agencies and municipalities,
and are available
at local libraries.
|
|
|
Q. |
Were
utilities and geotechnical
elements considered? |
A. |
All underground
and aerial utilities
were identified.
Utility base plans
were prepared.
Both geotechnical and
pavement assessments
were performed.
Subsurface information
was gathered.
|
|
|
Q. |
Will
there be increased
noise or pollution
to the area during
construction? |
A. |
The
contract documents
require the
construction contractor
to conform to all
federal and state
laws and regulations.
This includes environmental
regulations. Further
mitigation measures
are required
for construction
equipment, because
of nearby residences;
during the Final
Design phase Contract
Documents were
developed which
include these
mitigation measures.
|
|
|
Q. |
Will
they be working at
night? |
A. |
Construction
hours will be specified
to minimize disruption
to the local community.
However, some night
work that conforms
to local ordinances
may be required
to minimize disruption
to daily traffic
and optimize the
construction schedule.
|
|
|
Q. |
How
will local air quality
be affected by the
proposed improvements? |
A. |
Since
the focus of the
Route 3 improvements
is on safety and
improved access,
traffic flow will
be improved. Because
traffic flow will
improve and the
occurrences of
vehicles idling
in congested traffic
will be reduced
the overall effect
should be a decrease
in air pollution.
|
|
|
Q. |
Are
noise walls or other
sound barriers part
of the plan? |
A. |
Noise
studies performed
during Final Scope
Development determined
existing conditions
and the effects
of proposed construction
to identify where
noise mitigation
is warranted. During
the Preliminary
phase of the project,
mitigation measures
such as architectural
enhancement screens,
landscaping, etc.
were discussed
with local officials
and residents and
presented at October
2004 - Public Information
Centers. Each
of the three communities
(Rutherford, Clifton
and Lyndhurst)
adopted resolutions
in support of the
installation of
noise barriers.
Heights of the
noise barriers
were finalized
using the new profile
information.
|
|
|
Q. |
Will
any businesses or residences
need to be acquired
or relocated in order
to complete the proposed
improvements? |
A. |
Based
upon the current "smart
sized" projects,
two properties
in Rutherford lie
within the proposed
project footprint
(one is a vacant
lot). There are
also 13 residences
and five industrial
properties in Clifton
which were acquired.
The only Rutherford
residence affected
will not require
acquisition since
the Right of Way
impact is minor.
NJDOT has contacted
all affected property
owners when the
Right of Way acquisition
process began.
No properties in
Lyndhurst are
affected.
|
|
|
Q. |
How
does the reconstruction
of the Routes 3 and
46 Interchange affect
this project? |
A. |
The
reconstruction
at the Routes 46
and 3 interchange
is a separate NJDOT
project that includes
rehabilitation
of Route 3 from
the Grove Street
interchange in
Clifton to the
Route 46 interchange
with Notch and
Rifle Camp Roads
in Little Falls.
The Routes 46 and
3 interchange project
is presently in
the Design Phase
and that work should
have no impact
on this project.
|
|
|
Q. |
Is
this project related
to any pending development
projects in the Meadowlands
area? |
A. |
No.
The need for this
project has come
about over a period
of four decades
due to steady growth
in traffic volumes
and the construction
of interconnecting
state roads including
Route 21. The Concept
Development phase
of this project
began in 1992.
|
|
|
Q. |
How
will the proposed improvements
affect traffic patterns
on local streets? |
A. |
Traffic
engineering investigations
were performed
to determine the
impact of the proposed
project on local
traffic patterns
especially in residential
areas. Modifications
to the initial
design and other
strategies were
developed with
input from the
communities to
minimize any potential
negative impacts.
|
|
|
Q. |
How
is emergency access
being addressed throughout
the Route 3 project
area? |
A. |
The
safety and security
of highway users
is a paramount
goal of NJDOT.
This project is
based on the need
to improve safety
conditions. Emergency
access will be
enhanced throughout
much of the project
corridor.
|
|
|