Photos
(click on photos to enlarge)
June 2004
After traffic was switched to the new structure on June 8, 2004, the contractor began the demolition of the old swing span bridge. |
|
June 2004
The concrete bridge deck has been removed, as well as the steel girders, in the first three spans south of the navigational channel. |
|
June 2004
The contractor uses the existing bridge as a work platform as they demolish the old bridge. Barges are placed under the work area to catch falling debris. |
|
June 2004
After removing the deck on the old bridge, the contractor will demolish the bridge piers down below the mud line of the Raritan River. |
|
|
|